Cable Slack

<< Click to Display Table of Contents >>

Navigation:  IMS version 23.1 > IMS Basics - User Guide 23. > Geo Routing, Fiber Networks, and Outside Plant  > Cables >

Cable Slack

 

This topic covers:

 

oAdding Slack to a Cable

oUpdating Cable Slack

 


 

Fiber cables are given extra length to allow for future splicing work, and this is rolled up and placed in a manhole, handhole, or on a Pole. This extra length of cable is called slack and relevant information can be registered in the cable Circuit and Site objects. A cable's Circuit IMS form will not initially show Slack information. When Slack information is added, a new tab will appear in the Circuit form as well as the cable's related sites. These sites will be manhole, handhole, or pole types.

 


The Slack tab will appear in both the Circuit and Site objects that relate to the Cable circuit being worked on

 

Adding Slack to a Cable

 

When adding Slack information for the first time:

 


First go to the Circuit module, locate and place the required cable circuit in focus. This is achieved by clicking on the Put circuit in focus option in the Circuit Form Actions button bar. Cable circuits should be of the CBL type speeds i.e., CBL1, CBL24.

 

Once the required cable Circuit is in focus and then from the Network Map:

 

Right click on a related site that is a manhole, handhole, or pole.

 

01-01-GEO_Slack

 

From the drop down list provided, select New followed by the Add Slack option

 

This opens up the Add Slack popup window relating to the cable Circuit that is In Focus. The Circuit and Site fields are pre-filled.

 

01-02-GEO_Slack

 

If only the total length of cable slack is known (i.e., metres or feet):

 

Type in the number that represents the known length of Slack in field SlackA

 

If information is known about the markers on the cable Slack:

 

Type in the number representing the start marker in field SlackA

Type in the number representing the end marker in field SlackB

 

Click on the Save icon in the lower left corner of the popup window to complete this task

 

IMS will then calculate the difference and present this as the Slack Number in the Circuit Form. Returning to the cable in the Circuit module (or related Sites), the Slack tab is now visible. In the example screen shot below, 17 and 5 were entered and 12 is the calculated length of Slack.

 

01-03-GEO_Slack

 

 

Updating Cable Slack

 


Updating cable Slack information can be achieved from the related Circuit or Site object

 

When repairs or splicing has been carried out in the field that involves consuming cable slack length, then updates to the Slack information in IMS can be processed as follows:

 

From the Circuit or Site form relating to the Cable instance being worked on:

 

01-04-GEO_Slack_edit

 

Select the Slack tab

Click on the Edit icon - leftmost in the row

 

01-05-GEO_Slack_edit

 

Make the necessary adjustments to the figures in the SlackA and/or SlackB columns - in the above example only the SlackB field is modified

Click on the Save icon (green tick) - leftmost in the row to conclude the updating process.

The Slack Number field will automatically be adjusted.

 

01-06-GEO_Slack_edit